• Contact us
  • Advertising Policy
  • Cookie Policy
  • Disclaimer
  • Privacy Policy
  • Terms of Use
Monday, July 7, 2025
29 °c
Agartala
enewstime
  • Home
  • News
    • Northeast
    • National
    • International
    • Tripura News
  • Sports
    England were back to old ways after doing 'Bazball with brains' in Leeds: Vaughan

    England were back to old ways after doing 'Bazball with brains' in Leeds: Vaughan

    ICC appoints Sanjog Gupta as its new CEO

    ICC appoints Sanjog Gupta as its new CEO

    'I did think we declared late… but India won that's important': Dilip Vengsarkar

    'I did think we declared late… but India won that's important': Dilip Vengsarkar

    Shubman Shines, Akash Roars against England: India Breach Edgbaston Fortress

    Shubman Shines, Akash Roars against England: India Breach Edgbaston Fortress

    2nd Test: Start of day five play delayed due to heavy rain at Edgbaston

    2nd Test: Start of day five play delayed due to heavy rain at Edgbaston

    Deepika’s brilliant field goal against the Netherlands nominated for Poligras Magic Skill Award

    Deepika’s brilliant field goal against the Netherlands nominated for Poligras Magic Skill Award

    Vaibhav Suryavanshi sets sights on double century after record youth ODI ton

    Vaibhav Suryavanshi sets sights on double century after record youth ODI ton

    PM Modi arrives in Rio de Janeiro for BRICS Summit; city’s football spirit shines through

    PM Modi arrives in Rio de Janeiro for BRICS Summit; city’s football spirit shines through

    2nd Test: Had to check with Harry Brook if I was facing a hat-trick ball, reveals Jamie Smith

    2nd Test: Had to check with Harry Brook if I was facing a hat-trick ball, reveals Jamie Smith

  • Business
  • Entertainment
  • Health
  • Features
  • TendersNew
No Result
View All Result
  • Home
  • News
    • Northeast
    • National
    • International
    • Tripura News
  • Sports
    England were back to old ways after doing 'Bazball with brains' in Leeds: Vaughan

    England were back to old ways after doing 'Bazball with brains' in Leeds: Vaughan

    ICC appoints Sanjog Gupta as its new CEO

    ICC appoints Sanjog Gupta as its new CEO

    'I did think we declared late… but India won that's important': Dilip Vengsarkar

    'I did think we declared late… but India won that's important': Dilip Vengsarkar

    Shubman Shines, Akash Roars against England: India Breach Edgbaston Fortress

    Shubman Shines, Akash Roars against England: India Breach Edgbaston Fortress

    2nd Test: Start of day five play delayed due to heavy rain at Edgbaston

    2nd Test: Start of day five play delayed due to heavy rain at Edgbaston

    Deepika’s brilliant field goal against the Netherlands nominated for Poligras Magic Skill Award

    Deepika’s brilliant field goal against the Netherlands nominated for Poligras Magic Skill Award

    Vaibhav Suryavanshi sets sights on double century after record youth ODI ton

    Vaibhav Suryavanshi sets sights on double century after record youth ODI ton

    PM Modi arrives in Rio de Janeiro for BRICS Summit; city’s football spirit shines through

    PM Modi arrives in Rio de Janeiro for BRICS Summit; city’s football spirit shines through

    2nd Test: Had to check with Harry Brook if I was facing a hat-trick ball, reveals Jamie Smith

    2nd Test: Had to check with Harry Brook if I was facing a hat-trick ball, reveals Jamie Smith

  • Business
  • Entertainment
  • Health
  • Features
  • TendersNew
No Result
View All Result
enewstime
  • Home
  • News
  • Sports
  • Business
  • Entertainment
  • Health
  • Features
  • Tenders
Home Business

448 infra projects report cost overrun of over Rs 4.02 lakh cr

ENEWSTIME Desk by ENEWSTIME Desk
February 21, 2021
in Business
30
VIEWS
Share on FacebookShare on Twitter

As many as 448 central sector infrastructure projects have reported a cost overrun of over Rs 4.02 lakh crore as of February 21, 2021.

The monthly Flash Report by the Ministry of Statistics and Programme Implementation said that 539 projects are running behind schedule.

“Total original cost of implementation of the 1,739 projects was Rs 22,18,210.29 crore and their anticipated completion cost is likely to be Rs 26,20,618.44 crore, which reflects overall cost overruns of Rs 4,02,408.15 crore (18.14 per cent of original cost),” it said.

The expenditure incurred on these projects till January 2021 is over Rs 12.29 lakh crore, which is 46.92 per cent of the anticipated cost of the projects.

“Out of the 1,739 projects, 12 projects are ahead of schedule, 247 are on schedule, 539 are delayed, 448 projects reported cost overrun and 209 projects reported both time and cost overrun with respect to their original project implementation schedules,” it said.

The report however, noted that the number of delayed projects decreases to 401 if delay is calculated on the basis of latest schedule of completion. Further, for 941 projects neither the year of commissioning nor the tentative gestation period has been reported.

Related Posts

Union Minister Singh highlights Defence investment’s catalystic impact on India's economy
Business

Union Minister Singh highlights Defence investment’s catalystic impact on India's economy

July 7, 2025
Global capability centres show impressive 30.8 pc growth in India in Jan-June
Business

Global capability centres show impressive 30.8 pc growth in India in Jan-June

July 7, 2025
Listed firms' market cap up sharply in Q2 on stock rally in S. Korea
Business

Listed firms' market cap up sharply in Q2 on stock rally in S. Korea

July 7, 2025
Adani Enterprises announces Rs 1,000 crore NCDs offering up to 9.30 pc, issue opens July 9
Business

Adani Enterprises announces Rs 1,000 crore NCDs offering up to 9.30 pc, issue opens July 9

July 6, 2025
Rs 1 lakh crore fund to give big push to private sector R&D in robotics, AI & drones: DST Secretary
Business

Rs 1 lakh crore fund to give big push to private sector R&D in robotics, AI & drones: DST Secretary

July 6, 2025
Market outlook: India-US trade deal, Q1 FY26 earnings key drivers this week
Business

Market outlook: India-US trade deal, Q1 FY26 earnings key drivers this week

July 6, 2025
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT
D-2050 D-2050 D-2050
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT

About us

Enewstime.in is run by an individual – a Journalist by profession of Tripura with the active help of several journos including senior journalists of the State. On top of that, Enewstime.in being a subscriber of IANS news agency, we have plenty of multi-choice topics to offer to our esteemed readers. Enewstime.in is a venture reach global audience from a tiny State Tripura.

Latest News

IIT Delhi launches new online executive programme for AI in Healthcare

Shooting for Puri Jagannadh's film with Vijay Sethupathi begins in Hyderabad

Union Minister Singh highlights Defence investment’s catalystic impact on India's economy

England were back to old ways after doing 'Bazball with brains' in Leeds: Vaughan

Nipah positive patient in critical condition, says Kerala Health Minister

GFSRD celebrates World Rural Development Day 2025

Contact us

19, Old Thana Road. Banamalipur. PO. Agartala. Pin code 799001. Tripura (West), India.

Email: enewstime2017@gmail.com

Wa: 8794548041

  • Contact us
  • Advertising Policy
  • Cookie Policy
  • Disclaimer
  • Privacy Policy
  • Terms of Use

© 2025 Designed & Developed with ❤️ by Provibe Media LLP

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In
No Result
View All Result
  • Home
  • News
    • Northeast
    • National
    • International
    • Tripura News
  • Sports
  • Business
  • Entertainment
  • Health
  • Features
  • Tenders

© 2025 Designed & Developed with ❤️ by Provibe Media LLP