Tripura HC NHIDCL highway progress report
HC seeks NHIDCL compliance report, flags delays in national highway repairs

The High Court (HC) of Tripura directed NHIDCL to address concerns over national highway maintenance across the state, following complaints from the PWD about damaged road stretches, delayed contractual action, tendering problems and inadequate repair quality, with the agency required to submit its pending progress report by November 24.

At A Glance

  • Tripura High Court asks NHIDCL to submit its overdue bi-weekly progress report by November 24.

  • State PWD flags severe damage to NH-108B and NH-208 stretches, including over 64% damage on the Khowai-Srirampur section.

  • Court directs NHIDCL to examine concerns over repair quality, contractor management and tendering delays.

The Tripura High Court has sought an immediate review of highway maintenance work across the state after the Public Works Department (PWD) highlighted serious concerns over damaged roads, delayed repairs and shortcomings in contractor management. The court has directed NHIDCL to submit its pending progress report by November 24 and take corrective measures without further delay.

Court Flags Delay in NHIDCL Progress Report

A Division Bench comprising Chief Justice M.S. Ramachandra Rao and Justice S. Datta Purkayastha issued the directions while hearing a suo motu public interest litigation concerning national highway conditions in Tripura.

The Bench observed that the National Highways and Infrastructure Development Corporation Ltd (NHIDCL) had failed to submit its bi-weekly progress report after October 14. The agency had received a specific direction to submit such reports on September 8.

The court instructed NHIDCL to file the pending report by November 24 after providing an advance copy to the Advocate General.

During the hearing, the Advocate General presented the state government’s concerns based on observations by the PWD (National Highways). The department pointed to delays in contractual action, tendering procedures and the progress and quality of ongoing repair work.

Four Highway Packages Face Repair Concerns

The state government supported NHIDCL’s administrative action against defaulting engineering, procurement and construction (EPC) contractors. These measures included temporary suspensions and proceedings to terminate contracts.

However, the High Court expressed concern over repeated tendering delays caused by single-bidder non-responsiveness and technical disqualifications. It urged NHIDCL to streamline its procurement process.

The PWD highlighted problems across four highway packages:

– Package-II, NH-108B (Mohanpur-Subalsingh): A Special Observer identified serious structural and drainage damage. The department stressed that temporary repairs must lead to durable road reconstruction.

– Package-III, NH-108B (Subalsingh-Khowai): The PWD called for close monitoring of the existing contractor’s trial period. It sought immediate replacement if the contractor failed to meet road safety requirements.

– Package-IV, NH-208 (Srirampur-Bamanchara): The state urged NHIDCL to accelerate temporary repairs and expedite the appointment of a replacement contractor following the suspension and proposed termination of the existing agency.

– Package-V, NH-208 (Khowai-Srirampur): The department reported that more than 64% of the stretch had suffered severe damage. Deep potholes and distorted road surfaces posed serious concerns.

The PWD also warned that gravel-based temporary repairs could deteriorate rapidly during heavy rainfall without proper compaction and drainage arrangements.

State Seeks Better Project Planning and Supervision

The state government welcomed the findings of Special Observer Ravi Prasad and the Inception Report prepared by Intercontinental Consultants and Technocrats Pvt. Ltd.

Tripura HC NHIDCL highway progress report
HC seeks NHIDCL compliance report, flags delays in national highway repairs

It urged NHIDCL to incorporate their recommendations into the detailed project reports. These include underground drainage systems, hill-cut stability measures, cross-drainage structures and appropriate road gradients.

The PWD also insisted that NHIDCL’s additional field personnel remain physically present at construction sites. Their presence would help supervise J. Infratech Limited, the alternative agency responsible for maintenance work.

HC Orders Immediate Corrective Action

After considering the state’s submissions, the High Court directed NHIDCL to examine the concerns raised by the PWD and take appropriate corrective measures immediately.

The court has listed the matter for further hearing on November 24. NHIDCL must submit its pending progress report before that date.